Location: Calabasas, CA
Project Description: The Calabasas project will include the installation of a new 30-inch welded steel pipeline that will serve as a redundant system to supply potable water to the Calabasas area in case of an emergency. Our anticipated completion date is April 30th, 2014.
Project Management Team:
Project Executive -Josh Young and Chad Dessert
Senior Project Manager – Jim Ratliff
Project Manager – Eduardo Davila
Project Assistant – Vickie Hoang
Superintendent – Tony Zottola and Tim Soucie
Foreman – Brad Cruse, Brian Amacher and West King
General Contractor/Client: Las Virgenes Municipal Water District