Like many projects, the wastewater pump-station presents unique challenges such as limited work area, deep shored excavation and high ground water elevation. Even with a tight schedule among us, our Preston Pipelines team will pass through these obstacles with flying colors!
City: Santa Clara
Value: $2.5M
Year started: 2013
Project Management Team:
Project Manger – Dave Calandro
Superintendent – Ken Alexander
Project Assistant/Engineer – Ritu Giri
General Contractor/Client: Turner/Devcon Joint Venture